Enable Recite me Accessibility Tools:
Accessibility Options
To find out more, please see here.

We are looking forward to the completion of the building works in early spring for our new Macmillan Cancer Support Centre at Ashford Hospital. We will be sharing regular updates with photos as the building work progresses on this page and on our social media accounts.

Macmillan Support Centre Build

Courtyard before building works started

 

Floor Plan

Macmillan Support Centre Build

Click on this link to view the floor plan and artist impressions of the centre.

 

October 2025: Courtyard Clearing

Macmillan Support Centre Build

 
Macmillan Support Centre Build
Macmillan Support Centre Build

 
Macmillan Support Centre Build

Courtyard cleared

 

Macmillan Support Centre Build

 
Macmillan Support Centre Build
Macmillan Support Centre Build

 
Macmillan Support Centre Build

 

November 2025: Concrete and Steel

Macmillan Support Centre Build
 
Macmillan Support Centre Build
 
Macmillan Support Centre Build

 

Macmillan Support Centre Build

 
Macmillan Support Centre Build
 

Works done in preparation for the concrete to be poured

 

Macmillan Support Centre Build

Concrete has been poured

 

Macmillan Support Centre Build

Steelwork has started

 

Macmillan Support Centre Build

 
Macmillan Support Centre Build

Macmillan Support Centre Build

The steel frame was completed end of November. Part of the roof is now being prepared for installation in early December.

 

December 2025: Adding the Roof

Macmillan Support Centre Build

View of the roof from the second first floor

 

Macmillan Support Centre Build

 
Macmillan Support Centre Build

View of the inside of the structure as the building is taking shape

 

The roof is on and is now ‘weather tight’ which means the roof will keep the inside dry for the rest of the internal works to be completed, without being affected by the weather. Concrete upstands are being installed to support the external walls, doors and windows into the courtyard at the rear of the building. Preparation works are also being carried out for the skylights to be fixed to the roof.

The builders will be taking a well-earned break over the Christmas and New Year period and will be return to work from 5 January 2026.

 

March 2026: Building the Walls

Macmillan Support Centre Build

The building works are well underway. So far, we’ve seen the site being cleared, preparation work for the concrete base to be installed. Steelworks providing the frame and sturdy structure for the new building with the roof being added just before Christmas, making the building ‘weather tight’, which means the roof will keep the inside of the dry for the rest of the internal works to be completed, just in time before all the torrential rain.

Concrete stand ups were installed to support the external walls, doors and windows into the courtyard at the rear of the building to provide structural support and protect against water entering.

Essential fire-proofing has been completed. The frames for the skylights are now on the roof and the insulation has arrived and will be installed shortly. In addition to this there are preparation works taking place to build the floor.

 

The builders are progressing very quickly and are currently building the walls inside the Macmillan Cancer Support Centre. They’ve also taken the first steps in getting electricity and ventilation to the Centre installed. We should see more of these in the ceiling once the walls are finished ready for decorating.

Please see latest pictures below:

Macmillan Support Centre Build

View from the entrance showing the main space

 

Macmillan Support Centre Build

Macmillan Support Centre Build

Views of meeting room

 

Macmillan Support Centre Build

View from courtyard

 

Macmillan Support Centre Build

View of the quiet room

 

April 2026: Preparing for the Mechanical Equipment

The builders have progressed with the internal walls, and each room is now visible. They are installing brackets and accessories in preparation for engineers to fit the mechanical equipment on the ceilings to provide the centre with ventilation and climate control.

Outside, the ground is now being prepared for the paving to be installed.

Macmillan Support Centre Build

 
Macmillan Support Centre Build
Macmillan Support Centre Build

 
Macmillan Support Centre Build

Views from the main lobby / kitchen area

 

Macmillan Support Centre Build

View into the meeting room

 

Macmillan Support Centre Build

View of the courtyard

 

Macmillan Support Centre Build

View of the quiet room

 

May 2026: Paint, Plaster, and Paving

The site is the busiest it's been in the programme so far and there have been significant progress. More parts of the ventilation system have been installed including the ductwork. The side rooms have been plastered with the first coats of paint being applied, with the plasterers moving on to the meeting room and the main area. The garden has its paving slabs laid down.

Macmillan Support Centre Build

Macmillan Support Centre Build

Macmillan Support Centre Build

Meet and Greet and Kitchen Area

 

Macmillan Support Centre Build

Therapy Room

 

Macmillan Support Centre Build

Garden

 

June 2026: Doors and Floors

A lot of progress was made in the Macmillan site since the last update and we are heading ever closer to moving-in day!

Most of the cladding has gone up in the external wall at the back of the building:

Macmillan Support Centre Build

 
Macmillan Support Centre Build

 

The ventilation and air-conditioning system has now been installed and is being tested and commissioned. The builders are now installing the ceilings.

Macmillan Support Centre Build

 
Macmillan Support Centre Build
Macmillan Support Centre Build

 

 

The floor has been laid down. Protective sheets have been placed on top of it for the rest of the building work.

Macmillan Support Centre Build

 
Macmillan Support Centre Build

 

The sliding doors to the meeting room and the first of the glazed doors have arrived on site and are being fitted. The external openings are boarded up to protect the inside from the weather.

Macmillan Support Centre Build

 
Macmillan Support Centre Build

 

The built-in cupboards are now being installed:

Macmillan Support Centre Build

 
Macmillan Support Centre Build

 

View of the Kitchen:

Macmillan Support Centre Build

 

View of the Meet and Greet area:

Macmillan Support Centre Build

 

View from the corridor to the side rooms:

Macmillan Support Centre Build

 

View from above the site:

Macmillan Support Centre Build

 

 

July 2026: Ready for Inspection

The centre is now almost finished, with a couple of things and some finishing touches left to be installed by the contractors. We will then check the building for any snags while inspectors will check the building to make sure this meets building standards.

Once these are complete, we will start moving in with furniture and equipment. We are looking forward to seeing this with all the furniture inside.

 

Meet and Greet and Kitchen areas - the kitchen is almost complete:

Macmillan Support Centre Build

 
Macmillan Support Centre Build
Macmillan Support Centre Build

 
Macmillan Support Centre Build
Macmillan Support Centre Build

 
Macmillan Support Centre Build
Macmillan Support Centre Build

 

 

Office

Macmillan Support Centre Build

 
Macmillan Support Centre Build
Macmillan Support Centre Build

 

 

Meeting Room

Macmillan Support Centre Build

 
Macmillan Support Centre Build

 

Corridor - we are also preparing the corridor to the centre and the Infusion Suite for a fresh look:

Macmillan Support Centre Build

 
Macmillan Support Centre Build

 

Courtyard Garden - the paving has been revealed again:

Macmillan Support Centre Build

 
Macmillan Support Centre Build

 

Therapy Room

Macmillan Support Centre Build

 

 

July 2026: Finishing Touches

The building works are now complete and we are now beginning to move in, unpack furniture and set up our equipment. The walls have been decorated with lovely murals from a local artist, Michelle Sobihy, which provide a calming environment for the centre.

Our first group of volunteers have recently attended their induction and are getting ready for the centre to open.

 

Macmillan Support Centre Build

 

Kitchen area

 

Macmillan Support Centre Build

 

Meeting room from kitchen area

 

Macmillan Support Centre Build

 
Macmillan Support Centre Build

Artist Michelle Sobihy of Inspire Murals, painting murals

 

Macmillan Support Centre Build

 
Macmillan Support Centre Build

Murals in quiet room

 

Macmillan Support Centre Build

 

Welcome area and office

 

Macmillan Support Centre Build

 

Therapy room

 

Macmillan Support Centre Build

 

First group of volunteers with ASPH staff

 

Protecting Your Online Privacy
Protecting Your Online Privacy

This Ashford and St Peter's website uses cookies to track visitor numbers. Find out more in our Cookies Policy and Privacy Policy. You can also read our Accessibility Statement and Privacy Notice for your information.